Liberty State Park is closing its 50th year with crews at work on its eastern edge. The renovated Terminal Plaza is scheduled to be substantially complete before December. The first phase of the Historic Train Shed restoration was scheduled to begin in October. The fenced interior, the largest single piece of the state's plan, has a construction start no earlier than winter 2027/28. Every project with a near-term date sits at the end of the park you reach by walking south on the Hudson River Waterfront Walkway from Paulus Hook or Liberty Harbor.
So for the next year or two, the park's change happens at its front door, the Central Railroad of New Jersey Terminal and its surroundings. Its middle stays as it is.
The plaza at the end of Audrey Zapp Drive comes first
The Terminal Plaza is the paved space at the eastern end of Audrey Zapp Drive. In the Department of Environmental Protection's words, it connects the Empty Sky Memorial and the CRRNJ Terminal Building with the Hudson River Waterfront Walkway. DEP describes the work as a facelift meant to improve accessibility and make the space more welcoming to visitors.
The New Jersey Economic Development Authority oversees construction, and AECOM Tishman was selected as construction manager, according to DEP's January 14 release. The NJEDA's September 16, 2026 board book says plaza construction began in February 2026 and is expected to be "substantially complete prior to December of 2026." That's a ten-month job. As of its October 19 update, DEP's program page still says the plaza is "expected to reopen to visitors later in 2026," with no specific date.
Of all the pieces in the program, this is the only one with both a start date that has passed and a finish date inside this calendar year. It's also the one that matters most to anyone who arrives on foot. The plaza is where the walkway, the memorial and the Terminal meet.
The Train Shed is next, and it runs into 2027
Behind the Terminal stands the Historic Train Shed, the long covered structure where the rail platforms once ran. The NJEDA's amended agreement with DEP, approved in September, says its construction manager will "dismantle, stabilize, and restore a portion of the existing structure for potential public access," working in multiple stages, with work "expected to begin in October of 2026."
DEP's plan for that first phase is specific. It covers the east side of the shed, the part attached to the Terminal Building, and restores 60,000 square feet as flexible gathering and event space with seating and future interpretive programming. The same NJEDA update says demolition will be followed by a mockup or test section of the restoration, with the bid and award of the final restoration scope in 2027.
The agreement adds two smaller items, both clustered around the same corner. The first is more repair work and painting on the Terminal Building's concourse interior, façade and nearby features. The second is demolition of the warehouse on the Edward Hart property down to its foundation, which secures that site for future DEP development. The board book's project update expects construction on both to begin in fall 2026.
Put the plaza, the shed, the concourse and the warehouse together and the near-term program is almost entirely in the park's northeast corner.
Marina Green and the interior wait their turn
In January, DEP named Marina Green's athletic fields and picnic space among its priority projects, alongside the plaza and the shed, and projected public openings "in the second half of 2026 and into 2027." DEP's Marina Green page, dated December 2025, said only that groundbreaking was expected in 2026.
The September NJEDA update reorders things. It says the added work scopes take precedence over Marina Green and the new Audrey Zapp Drive Gateway, and it gives neither a construction or opening date.
The interior is further out still. DEP's restoration project page, updated October 1, describes it as "currently fenced off and inaccessible." The plan is to turn it into tidal and non-tidal wetlands, upland forest and grassland, with trails, wildlife observation structures and signage. DEP says the work will link "previously developed and restored, but isolated, components of the park into one cohesive whole."
Here is how the sequence lines up, using each agency's own timing:
| Project | Location in the park | Stated timing |
|---|---|---|
| Terminal Plaza | East end of Audrey Zapp Drive, at the walkway | Began February 2026; substantially complete before December 2026 |
| Historic Train Shed, phase one | East side of the shed, attached to the Terminal | Expected to begin October 2026; final restoration scope bid and awarded in 2027 |
| Terminal concourse repairs | CRRNJ Terminal interior and façade | Construction expected to begin fall 2026 |
| Edward Hart warehouse demolition | 1 Edward Hart Drive | Construction expected to begin fall 2026 |
| Marina Green fields and picnic space | Marina Green | Openings projected second half of 2026 into 2027; now ranked behind the added scopes |
| Interior restoration | Fenced central acreage | 100% plans winter 2026/27; bid spring/summer 2027; award fall 2027; construction begins winter 2027/28 |
Interior construction starts more than a year after the plaza and shed work. Even then, that date only marks when crews begin.
The 50th year already happened at the same end
DEP's assistant commissioner for State Parks, Forests & Historic Sites, John Cecil, told ROI-NJ this month that the park "celebrates its 50th year" under a long-term vision set in the August 2025 Liberty State Park Master Plan.
Much of the anniversary programming was staged at the Terminal. Friends of Liberty State Park put on "The People's History of LSP," a history-and-art exhibition in the Terminal's Blue Comet Auditorium, from September 19 through October 18. A Jersey City Times review, reprinted by the Friends, noted free admission and hours of 8:30 a.m. to 5 p.m. Earlier in the year, Run LSP marked the anniversary on June 14 with a 5K at 9:30 a.m. and a children's run at 10:30. The park's free weekend shuttle ran May 23 through September 6.
All of that is over. What's left of 2026 runs on the park's ordinary late-season schedule, plus a few dated events at and next to it.
November and December, by date
The Terminal Building keeps winter hours. DEP lists it as open 8 a.m. to 4:30 p.m. in November and December, and closed on Thanksgiving.
- November 10. Surati for Performing Arts holds its Diwali Gala & Festival at Liberty Science Center, 5 to 11 p.m.
- November 12. LSC After Dark presents "Emo Night," with themed laser and planetarium shows.
- November 14. The NY Skyline Half Marathon, 10K and 5K runs at Liberty State Park.
- Thanksgiving Day. The CRRNJ Terminal is closed, and Statue City Cruises runs no service from the park.
- Christmas Day. Statue City Cruises runs no service. Otherwise it lists daily departures from the park to Liberty and Ellis islands, on times that change by season.
- Through January 3, 2027. LSC's "Power of Poison" and "Thomas & Friends: Explore the Rails" both stay open through that date.
Liberty Science Center has its own construction underway. Project Supernova, a $40 million expansion, broke ground on September 10, 2026. LSC lists a goat-and-kid play area, a river otter habitat, physics mini-golf, a 9/11 memorial garden and a pollinator garden among its features.
The marina corner keeps its own hours
The park's northern edge runs on a separate rhythm. The restaurant once called Liberty House Restaurant now operates as Maddy Rose at Liberty House. Its posted hours are:
- Lunch Wednesday through Friday, noon to 3 p.m., and Saturday and Sunday, 11 a.m. to 3 p.m.
- Dinner Wednesday and Thursday, 5 to 10 p.m.; Friday and Saturday, 5 to 11 p.m.; Sunday, 5 to 9 p.m.
The restaurant is closed Monday and Tuesday.
DEP's park page lists Liberty Landing Marina with 250 slips, transient dockage, dry storage, 24-hour fuel, maintenance and a marine store. Maritime Parc is also on site. The Liberty Landing Ferry connects the marina with Warren Street and Brookfield Place, so you can cross to Lower Manhattan from the park's edge without heading back to Exchange Place.
For anyone living along the walkway in Paulus Hook or elsewhere on the Jersey City waterfront, the park reaches you in two places: the marina by ferry, and the Terminal on foot. The Terminal end is where the state is spending first. If the NJEDA schedule holds, the renovated plaza reopens before December, and work on the Train Shed beside it continues into 2027.
Hudson Realty Group follows projects like the Terminal Plaza and the Train Shed because they change how a walk from the waterfront blocks feels long before they show up anywhere else. If you're weighing a home near the park or along the walkway, Contact Us and we'll go through what's scheduled near the blocks you're considering.